Arkaroo Rock Project timeline
By November 2020 - Completed
- Targeted stakeholder consultation
- Initial project concepts developed
- Feedback to stakeholders and community delivered
By December 2020 - Completed
- Detailed infrastructure designs developed
By February 2021 - Commenced
- Construction tender open
By May 2021
- Construction work commences
By September 2021
- Construction work completed and new visitor experience opens at Arkaroo Rock.
Brachina Gorge Geological Trail Project timeline
By December 2020 - Completed
- Concept planning for infrastructure and interpretation upgrades
By June 2021 - Commenced
- Interpretation research and development
Beyond July 2021
- Any further stages of works for the Brachina Gorge Geological Trail is subject to further funding and is yet to be confirmed.